Projects

Alathur ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
District Thrissur
LAC Puthukkad
Location
Project Details
Actual Start Date 19.04.2018
Project Management Consultant ISA
Category Road Over Bridges
LC No 33
Railway (km) 51/600-700
Length Including Approaches 335.44
Width of ROB 10.20
GAD Status Not approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.51
Funded By KIIFB
Project Outlay(crores) 21.87
Work Progress Details
Physical progress 75 %
Current status Final GAD & alignment plan submitted to Railways on 17.02.2022. Vide letter dated 11.07.2022, Railway informed that GAD of ROB’s between Ernakulam and Shornur will be approved only after finalization of 3rd line. Alignment of 3rd and 4th line received from Railway. GAD submitted to railways on 01.01.2026. Maintenance Agreement Shared on 20.05.2026. Awaiting approval of GAD from Railways.