| Current status |
DPR approved on 06.08.2020 for an amount of Rs. 33.19Cr.
On 11.07.2022, Railway had given in-principle approval for starting the land acquisition.
On 21.03.2023, Railway informed that this ROB proposal is falling on the alignment of
proposed 3rd & 4th Line between Coimbatore and Shornur and hence the GAD is kept on
hold. On 19.07.2024 Railways requested to revise the GAD. After several revisions, the
revised GAD was submitted on 01.01.2026.
LA requisition submitted to District Collector on 29.10.2022. 4(1) published on
26.07.2024. 11(1) notification published on 19.05.2025. 19(1) notification published on
12.03.2026. Awaiting GAD approval from Railway. |