Current status |
DPR approved by KIIFB on 09.08.2020 for an amount of Rs.40.40 Cr.
A joint site inspection was carried out with NHAI and ULCCS representatives on 18.10.2021 at Manjeshwar. On 20.10.2021 NHAI sent a letter and requested to modify the alignment. Accordingly, RBDCK directed consultant M/s ISA to revise the drawing of Manjeshwar ROB on 05.11.2021. But, consultant M/s ISA informed that they required both vertical and horizontal alignments of the NH project under execution to suit the profile. The details are collected from NHAI and based on the same GAD was modified and submitted to NHAI and Railways for concurrence on 07- 05-2022. Vide letter dated 26.05.2022, Railways informed that the GAD found ok. Reminders for getting Concurrence were submitted to NHAI on 22.07.2022 and 18.11.2022. On 30.11.2022 Sr. Project Manager ULCCS informed that they have verified the GAD forwarded by RBDCK and found that it is not obstructing / intervening, the approved alignment of NH66 and we can proceed further.
On 16.09.2023 requested Secretary to government for getting NOC from NHAI for the construction.
GAD approved by Railways on 13.02.2024. LA plan prepared and requisition submitted to District Collector on 02.05.2024. Quotation invited for boundary stone planting. |