Current status |
DPR approved by KIIFB on 09.08.2020 for an amount of Rs.28.39 Cr. LA to be taken up after getting approval of GAD from railways.
Project was pending due to Semi High Speed Rail project of KRDCL. On 06.12.2022, KRDCL had informed to go ahead with the construction of ROBs without considering the silver line alignment and RBDCK intimated the same to Railways on 08.12.2022. Railways directed to submit revised GAD for all ROBs long pending due to Silver line vide letter dated 14.03.2023.
Appointed the Consultancy M/s JH for the revision of GAD and alignment on 17.03.2023. LUS inspection conducted on 04.07.2023 and report received. Revised GAD submitted on 03.10.2023. The Railways had informed that all the future ROB superstructures are to be designed for Special Vehicle Loading. RBDCK had already requested for RDSO drawings vide letters dated 14.03.2024 and 06.05.2024. As per the above direction, all the pending GADs can be submitted only after the receipt of the RDSO drawings for Special Vehicle Loading. |