General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.46/2020/PWD | 13.01.2021 | 52.08 | |
District | Kollam | ||
LAC | Eravipuram | ||
Location |
Project Details | |
---|---|
Category | Road Over Bridges |
LC No | 549 |
Railway (km) | 162/000-100 |
Length Including Approaches | 462.811 m |
Width of ROB | 10.20 m |
GAD Status | Not Approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 22.51 |
Revised AS Amount(crores) | 52.08 |
Funded By | KIIFB |
Project Outlay(crores) | 52.24 |
Work Progress Details | |||
---|---|---|---|
Current status | DPR approved by KIIFB on 20.03.2022. GAD approved by Railways on 08.08.2022. LA requisition submitted to District Collector Kollam on 27.08.2022. Sp. Tahsildar KIIFB Kollam is appointed as LAO. Boundary stone planting completed and Joint inspection conducted on 13.06.2023. Contingency charge of Rs. 50 lakh released to LAO on 09.08.2023. 4(1) notification published on 20.09.2023. SIA study completed. Expert committee report submitted. 11(1) notification published on 14.11.2024. Survey and Structural works in progress. |