| General Details | |||
|---|---|---|---|
| Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
| Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO(Rt)No.46/2020/PWD | 13.01.2021 | 52.08 | |
| District | Kollam | ||
| LAC | Eravipuram | ||
| Location | |||
| Project Details | |
|---|---|
| Category | Road Over Bridges |
| LC No | 549 |
| Railway (km) | 162/000-100 |
| Length Including Approaches | 462.811 m |
| Width of ROB | 10.20 m |
| GAD Status | Not Approved |
| No of Lanes | 2 |
| Financial Details | |
|---|---|
| AS Amount(crores) | 22.51 |
| Revised AS Amount(crores) | 52.08 |
| Funded By | KIIFB |
| Project Outlay(crores) | 52.24 |
| Work Progress Details | |||
|---|---|---|---|
| Current status | DPR approved by KIIFB on 20.03.2022. GAD approved by Railways on 08.08.2022. LA requisition submitted to District Collector Kollam on 27.08.2022. S 11(1) notification published on 14.11.2024. Survey and Structural valuation works in progress. | ||