General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.46/2020/PWD | 13.01.2021 | 52.08 | |
District | Kollam | ||
LAC | Eravipuram | ||
Location |
Project Details | |
---|---|
Category | Road Over Bridges |
LC No | 549 |
Railway (km) | 162/000-100 |
Length Including Approaches | 462.811 m |
Width of ROB | 10.20 m |
GAD Status | Not Approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 22.51 |
Revised AS Amount(crores) | 52.08 |
Funded By | KIIFB |
Project Outlay(crores) | 52.24 |
Work Progress Details | |||
---|---|---|---|
Current status | DPR approved by KIIFB on 20.03.2022. GAD approved by Railways on 08.08.2022. LA requisition submitted to District Collector Kollam on 27.08.2022. S 11(1) notification published on 14.11.2024. Survey and Structural valuation works in progress. |