Projects

Kurikad ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
District Ernakulam
LAC Piravom
Project Details
Category Road Over Bridges
LC No 11
Railway (km) 13/500-600
Length Including Approaches 428.17m
Width of ROB 10.20 m
GAD Status Approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.51
Funded By KIIFB
Project Outlay(crores) 36.89
Work Progress Details
Current status DPR approved on 06.08.2020 for an amount of Rs.36.89 Cr. GAD approved by Railways on 25.07.2022. LA Requisition submitted to District Collector, Ernakulam and request for Revenue (B) Sanction submitted to Secretary PWD on 22.09.2022. 11(1) notification published. Structural valuation is progressing. BVR under preparation.