General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
District | Ernakulam | ||
LAC | Piravom |
Project Details | |
---|---|
Category | Road Over Bridges |
LC No | 11 |
Railway (km) | 13/500-600 |
Length Including Approaches | 428.17m |
Width of ROB | 10.20 m |
GAD Status | Approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 22.51 |
Funded By | KIIFB |
Project Outlay(crores) | 36.89 |
Work Progress Details | |||
---|---|---|---|
Current status | DPR approved on 06.08.2020 for an amount of Rs.36.89 Cr. GAD approved by Railways on 25.07.2022. LA Requisition submitted to District Collector, Ernakulam and request for Revenue (B) Sanction submitted to Secretary PWD on 22.09.2022. 11(1) notification published. Structural valuation is progressing. BVR under preparation. |