Projects

Punnol ROB (Kuriyanchil)

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
District Kannur
LAC Thalassery
Location
Project Details
Actual Start Date 19.04.2018
Project Management Consultant ISA
Category Road Over Bridges
LC No 224
Railway (km) 728/300-400
Length Including Approaches 437.72 m
Width of ROB 10.20 m
GAD Status Not Approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.51
Funded By KIIFB
Project Outlay(crores) 38.56
Work Progress Details
Physical progress 74 %
Current status DPR approved by KIIFB on 09.08.2020. LA to be taken up after getting approval of GAD from railways. KRDCL informed that the project comes under the alignment of Semi High Speed Rail project & required revision as per modifications suggested by KRDCL. In the case of ROBs coming under silver line alignment, Railways has informed that the GAD's of the silver line affected ROB's will be considered only after the approval of silver line alignment by Railway board. Now, KRDCL has intimated Railway to process the GAD's of ROB's entrusted to KRDCL without considering the silver line alignment. Hence on 26.08.2022, RBDCK has requested KRDCL to give direction to Railways to process the GAD's of ROB's which is coming under Silver-line without considering the silver line alignment in the case of RBDCK also. Accordingly vide letter dated 28.09.2022, KRDCL informed that RBDCK can proceed with the construction of ROBs as per the approved GADs without considering the silver line alignment. RBDCK intimated the same to Railways on 12.10.2022. But vide letter dated 26.10.2022, Railways instructed RBDCK to obtain clarification from KRDCL whether the alignment given is applicable for ROB’s for which GAD are yet to be approved. Accordingly on 03.11.2022, RBDCK requested KRDCL for clarification in case of ROBs which are awaiting GAD approval from Railways. Awaiting reply from KRDCL.