Ezhupunna ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
District Alappuzha
LAC Aroor
Location
Project Details
Actual Start Date 19.04.2018
Project Management Consultant KITCO Ltd
Category Road Over Bridges
LC No 17
Railway (km) 18/0-100
Length Including Approaches 765.46 m
Width of ROB 9.75 m
GAD Status Not Approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.51
Funded By KIIFB
Work Progress Details
Physical progress 57 %
Current status DPR approved by KIIFB on 30.06.2025 and GAD submitted to Railways on 04/03/2025. The Railway adopted certain RDSO Standard drawings for the GAD, which were forwarded to the consultant for incorporating the changes and resubmission. Revised GAD submitted to Railway on 21.01.2026.