| General Details | |||
|---|---|---|---|
| Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
| District | Alappuzha | ||
| LAC | Aroor | ||
| Location | |||
| Project Details | |
|---|---|
| Actual Start Date | 19.04.2018 |
| Project Management Consultant | KITCO Ltd |
| Category | Road Over Bridges |
| LC No | 17 |
| Railway (km) | 18/0-100 |
| Length Including Approaches | 765.46 m |
| Width of ROB | 9.75 m |
| GAD Status | Not Approved |
| No of Lanes | 2 |
| Financial Details | |
|---|---|
| AS Amount(crores) | 22.51 |
| Funded By | KIIFB |
| Work Progress Details | |||
|---|---|---|---|
| Physical progress | 57 % | ||
| Current status | DPR approved by KIIFB on 30.06.2025 and GAD submitted to Railways on 04/03/2025. The Railway adopted certain RDSO Standard drawings for the GAD, which were forwarded to the consultant for incorporating the changes and resubmission. Revised GAD submitted to Railway on 21.01.2026. | ||