Projects

Ezhupunna ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
District Alappuzha
LAC Aroor
Location
Project Details
Actual Start Date 19.04.2018
Project Management Consultant KITCO Ltd
Category Road Over Bridges
LC No 17
Railway (km) 18/0-100
Length Including Approaches 765.46 m
Width of ROB 9.75 m
GAD Status Not Approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.51
Funded By KIIFB
Work Progress Details
Physical progress 57 %
Current status RBDCK had prepared DPR and submitted to KIIFB for approval. KIIFB had requested to revise the DPR with the alignment on existing road on 10.09.2021. The work was tendered on 07.02.2022 for the preparation of revised DPR. Agreement was executed with M/s ISA on 17.06.2022. Topographic survey completed. Comparative Study Report submitted by the consultant on 01.11.2022. Meeting was conducted with MLA for the finalisation of alignment on 19.11.2022. Alignment report submitted to KIIFB for approval on 14.03.2023 and on 03.05.2023, KIIFB has directed to submit the DPR. Soil investigation works completed. Meanwhile, MLA directed to include junction development in the proposal vide letter dated 15.06.2023.