| Current status |
DPR approved by KIIFB on 07.09.2021 for an amount of Rs.31.97 Cr. GAD approved by Railways on 10.11.2023.
LA requisition submitted on 23.01.2024 4(1) notification published on 23.08.2024. SIA study report submitted to District Collector. Expert committee on 06.02.2025 has advised to Expedite another alignment, as suggested by SIA agency. The suggestion was studied by RBDCK and the report mentioning the salient features and drawbacks was submitted to Expert committee. The Expert Committe has been submitted to the District Collector. Accordingly, the District Collector has been directed to carry out the work as per the previously approved alignment. The 11(1) notification was publised on 25.09.2025. LA work in progress. |