Projects

Punnamoodu ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.46/2021/PWD 13.01.2021 37.16
District Thiruvananthapuram
LAC Varkala
Location
Project Details
Actual Start Date 19.04.2018
Project Management Consultant ISA
Category Road Over Bridges
LC No 558
Railway (km) 177/800-900
Length Including Approaches 342.32 m
Width of ROB 10.20 m
GAD Status Not Approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.51
Revised AS Amount(crores) 37.16
Funded By KIIFB
Project Outlay(crores) 36.88
Work Progress Details
Physical progress 60 %
Current status DPR was approved by KIIFB on 20.03.2022. LA to be taken up after getting approval of GAD from railways. Final GAD was submitted to railways on 15.03.2022.