General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.46/2021/PWD | 13.01.2021 | 51.37 | |
District | Thiruvananthapuram | ||
LAC | Kazhakkoottam |
Project Details | |
---|---|
Actual Start Date | 19.04.2018 |
Project Management Consultant | ISA |
Category | Road Over Bridges |
LC No | 574 |
Railway (km) | 203/13-14 |
Length Including Approaches | 684.40m |
Width of ROB | 10.20 m |
GAD Status | Not Approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 22.51 |
Revised AS Amount(crores) | 51.37 |
Funded By | KIIFB |
Project Outlay(crores) | 53.91 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 60 % | ||
Current status | DPR approved by KIIFB on 20.03.2022. KRDCL informed that the project comes under the alignment of Semi High Speed Rail project & required revision as per modifications suggested by KRDCL. Hence, RBDCK requested Railways whether we can proceed with the GAD modifications as suggested by KRDCL vide letter dated 25.09.2021. RBDCK has requested KRDCL to inform a convenient date for Joint Inspection on 08.02.2022 and a reminder letter sent on 24.03.2022, awaiting reply. |