Current status |
A single ROB alignment was prepared in between Sarkara & Manjadimoodu level cross and forwarded to Railways for their concurrence on 20.05.2022.
In the mean time Letter had issued to ISA for examine/modify the independent alignments through existing road. Independent alignments was submitted by M/s ISA on 22.08.2022. Later, Railway had informed that the single ROB proposal is feasible at site and instructed to submit the GAD along with alignment.
During the review meeting by CAO & CE RSP on 08.10.2024 it was decided to conduct a site visit prior to the submission of GAD. On 18.10.2024, RBDCK had requested CE/RSP for a tentative date for Joint site Inspection and inspection conducted on 18.11.2024. In accordance with the instruction outlined, a single ROB was proposed in Lieu of LC No. 567&569 and the alignment was subsequently submitted to the Railways for their concurrence. But on review meeting conducted by CAO/RSP on 10.01.2025, it was advised to propose two separate ROBs at LC's. Letter was submitted to Railways on 04.06.2025 requesting official instruction to submit separate GAD for the ROBs. |