| Current status |
A single ROB alignment was prepared in between Sarkara & Manjadimoodu level cross and forwarded to Railways for their concurrence on 20.05.2022.
In the mean time Letter had issued to ISA for examine/modify the independent alignments through existing road. Independent alignments was submitted by M/s ISA on 22.08.2022. Now Railway had informed that the single ROB proposal is feasible at site and instructed to submit the GAD along with alignment.
Appointed Consultant M/s RITES for DPR preparation on 17.03.2023. During the review meeting by CAO & CE RSP on 08.10.2024 it was decided to conduct a site visit prior to the submission of GAD. On 18.10.2024, RBDCK had requested CE/RSP for a tentative date for Joint site Inspection and inspection conducted on 18.11.2024. But on review meeting conducted by CAO/RSP on 10.01.2025, it was advised to propose two separate ROBs at LC's. Letter was submitted to Railways on 04.06.2025 requesting official instruction to submit separate GAD for the ROBs. |