Current status |
A single ROB alignment was prepared in between Sarkara & Manjadimoodu level cross and forwarded to Railways for their concurrence on 20.05.2022.
In the mean time Letter had issued to ISA for examine/modify the independent alignments through existing road. Independent alignments was submitted by M/s ISA on 22.08.2022 and is under scrutiny. Now Railway had informed that the single ROB proposal is feasible at site and instructed to submit the GAD along with alignment.
Appointed Consultant M/s RITES for DPR preparation on 17.03.2023. During the review meeting by CAO & CE RSP on 08.10.2024 it was decided to conduct a site visit prior to the submission of GAD. On 18.10.2024, RBDCK had requested CE/RSP for a tentative date for Joint site Inspection and inspection conducted on 18.11.2024. The GAD will be revised as per the Minutes of Meeting and submitted for approval. |