General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
District | Thiruvananthapuram | ||
LAC | Nedumangad | ||
Location |
Project Details | |
---|---|
Actual Start Date | 19.04.2018 |
Project Management Consultant | ISA |
Category | Road Over Bridges |
LC No | 573 |
Railway (km) | 202/700-800 |
Length Including Approaches | NOT FINALISED |
Width of ROB | NOT FINALISED |
GAD Status | NOT FINALISED |
No of Lanes | NOT FINALISED |
Financial Details | |
---|---|
AS Amount(crores) | 22.51 |
Funded By | KIIFB |
Work Progress Details | |||
---|---|---|---|
Physical progress | 30 % | ||
Current status | Alignment will be finalized after the approval of GAD from Railways. GAD is submitted to Railways for approval. Project was pending due to Semi High Speed Rail project of KRDCL. On 06.12.2022, KRDCL had informed to go ahead with the construction of ROBs without considering the silver line alignment and RBDCK intimated the same to Railways on 08.12.2022. Railways directed to submit revised GAD for all ROBs long pending due to Silver line vide letter dated 14.03.2023. Appointed Consultant M/s RITES for DPR preparation on 17.03.2023. |