Current status |
DPR submitted to KIIFB on 27.08.2021. KIIFB issued TAR on 15.02.2022. Clarification on TAR submitted to KIIFB on 11.04.2022. TAR 2 issued by KIIFB on 27.05.2022. As directed by KIIFB, fresh traffic survey conducted and Clarification on TAR 2 has submitted to KIIFB on 30.09.2022.
In the review meeting of KIIFB projects under Kanhangad LAC on 21/09/2023, based on discussion with MLA, KIIFB informed that the project is on deferring due to low traffic at the concerned junction which does not meet the IRC criteria for a flyover. In view of the above, contract with M/s EI Technologies Pvt. Ltd. was foreclose on 26.03.2024. |