Projects

Ponnani Cable Stayed Bridge

Back View Alignment

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No 942/2017/PWD 10.07.2017 100
Revised Administrative Sanction Order Number Dated Amount(crores)
GO (Rt) No. 671/2019/PWD 31.05.2019 236
District Malappuram
LAC Thavanur , Ponnani
Location
Project Details
Project Management Consultant L & T
Category River Bridges
Length including approaches 2550 & 760
Width of Bridge 23
No of Lanes 4
Financial Details
AS Amount(crores) 100
Revised AS Amount(crores) 236
Funded By KIIFB
Project Outlay(crores) 280.09
Work Progress Details
Current status DPR approved on 06.11.2020 for an amount of Rs.280.09 Cr. CRZ clearance was obtained from KCZMA on 17.09.2022. LA in progress. 4(1) notification published. 11(1) published on 08.11.2022. In accordance with Government order G.O. (MS) No. 50/2023/RD dated 10.03.2023 a special Rehabilitation and Resettlement (RR) package has been introduced for stakeholders of the coastal highway. Since, Ponnani cable stayed Bridge is a part of coastal highway, Revenue secretary have directed on 23.11.2024 special RR package also applicable for this project. LA fund request for an amount of Rs. 38,17,75,994/- submitted by Tahsildar. The same was deposited to Tahsildar on 25.03.2025.
View Alignment