Current status |
Entrusted to RBDCK on 25.02.2020. For preparation of DPR, LOA issued to M/s Velcity on 15.09.2020. Alignment report submitted by consultant was approved by RBDCK. Directed Consultant to Submit the Draft DPR. Meeting convened by MLA on 10.02.2022 in the presence of representatives of Koduvally Municipality and suggested to include the junction development. Direction given to the consultant for the same.
DPR under preparation. Instructed M/s Velcity to restrict the slope below 7.85% ( 1 in 12.75) Site inspection was conducted by the consultant on 11.05.2022. DPR Submitted on 20.07.2022 but returned for correction. Corrected DPR submitted by the DPR Consultant 26.12.2022 and Returned for corrections on 09.01.2023.
Now DPR consultant submitted the draft DPR after all the corrections instructed vide mail dated 09.01.2023 on 08.02.2023 (by mail and informed hard copy will be submitted on 13.02.2023).
The same is submitted to AD confirmation in the KIIFB portal on 12.02.2023. KIIFB inspection convened and PAD instructed to change the end portion of alignment. Since NH has a proposal of bypass to by-pass the Thamarasery Chunkam Junction, PAD informed to get the clarification for the same from PWD, NH. Compliance report for QAP is submitted to KIIFB. FS for Land acquisition issued on 13/03/2024 for an amount of Rs 74,38,52,300/-. Directed M/s Velcity consultant (PMC for DPR) to prepare LA plan for furthur procedures. M/s Velcity informed village plan survey records of some parts for proposed link road is not available in the concerned Revenue office. Hence requested for 1 more month time to submit the LA plan. |