| Current status |
Appointed consultant M/s RITES for DPR preparation. They had submitted the draft alignmnet proposal. To discuss the matters regarding alignment, a meeting with Hon'ble MLA was conducetd on 12.12.2023. GAD submitted to Railways on 20/02/2024. Site inspection with SSE Railways conducted on 30/05/2024. GAD returned to RBDCK by the railways for incorporating corrections. Corrected GAD submitted to Railways on 15.10.2024. Awaiting approval from Railways. Also, requested to inform the P& E charge amount. Requested ADEN, Thrissur (Southern railways) to intimate a convenient date for joint inspection, as directed by DRM/(Southern railways). Joint Inspection conducted on 01.08.2025. Awaiting P&E charge intimation from Railway. Feasibility report submitted on 11.10.2025 and awaiting for confirmation. Joint feasibility report resubmitted on 19.12.2025. Updated GAD submitted on 21.01.2026. Awaiting for confirmation. |