General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO (Rt) 807/2017/H.Ed | 29.04.2017 | 240.9 | |
Technical Sanction | Order Number | Dated | Amount(crores) |
RBDCK/ T220/ TS-05/ 2018-19 | 13.04.2018 | 8.21 | |
District | Ernakulam | ||
LAC | Ernakulam | ||
Location |
Project Details | |
---|---|
Completion Date | 31.08.2021 |
Funding | KIIFB |
Category | Building Projects |
Type | Academic Building |
Description | Construction of academic building at lake side campus |