Eravipuram ROB

Back View Progress

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 20
Technical Sanction Order Number Dated Amount(crores)
RBDCK/T 301/TS-22/2021-22 03.11.2021 24.51
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.132/2017/PWD 04.02.2017 40.49
District Kollam
LAC Eravipuram
Location
Project Details
Actual Start Date 04.01.2021
Contractor(s) M/s SPL Infrastructure Pvt. Ltd
Project Management Consultant RITES
Category Road Over Bridges
LC No 547
Railway (km) 159/800-900
Length Including Approaches 411.27
Width of ROB 10.05
GAD Status APPROVED
No of Lanes 2
Financial Details
AS Amount(crores) 20
Revised AS Amount(crores) 40.49
Funded By KIIFB
Project Outlay(crores) 31.6
TS Amount(crores) 24.51
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/ROB/T301/ROB/14 25.06.2020 222.7
Agreement Details
Agreement No Agreement Date Agreed Amount(crores) Site Handover Date Period of Completion Actual Date of Completion
RBDCK/ROB/T44/28/2021 04.01.2021 251.48 12 Months
Work Progress Details
Physical progress 75 %
Current status All works upto deck slab completed. Diaphragm 7/12 completed. Balance Diaphragm, Road work & drain works in progress. Railway Portion - Girder erection, 3/3 deck slab and crash barrier completed. Parapet wall and wearing coat works in progress.