| General Details | |||
|---|---|---|---|
| Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO(Rt)No.1324/2016/PWD | 27.09.2016 | 20 | |
| Technical Sanction | Order Number | Dated | Amount(crores) |
| RBDCK/T 301/TS-19/2021-22 | 18.10.2021 | 19 | |
| Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO(Rt)No.132/2017/PWD | 04.02.2017 | 37.38 | |
| District | Kannur | ||
| LAC | Thalassery | ||
| Location | |||
| Project Details | |
|---|---|
| Actual Start Date | 04.01.2021 |
| Contractor(s) | M/s SPL Infrastructure Pvt. Ltd |
| Project Management Consultant | RITES |
| Category | Road Over Bridges |
| LC No | 230 |
| Railway (km) | 738/3-4 |
| Length Including Approaches | 313.60 |
| Width of ROB | 10.05 |
| GAD Status | APPROVED |
| No of Lanes | 2 |
| Financial Details | |
|---|---|
| AS Amount(crores) | 20 |
| Revised AS Amount(crores) | 37.38 |
| Funded By | Government |
| Project Outlay(crores) | 26.42 |
| TS Amount(crores) | 19 |
| Tender Details | |||
|---|---|---|---|
| Tender No | Dated | Tender Amount(crores) | RBDCK/ROB/T301/ROB/14 | 25.06.2020 | 222.7 |
| Agreement Details | |||||||
|---|---|---|---|---|---|---|---|
| Agreement No | Agreement Date | Agreed Amount(crores) | Site Handover Date | Period of Completion | Actual Date of Completion | ||
| RBDCK/ROB/T44/28/2021 | 04.01.2021 | 251.48 | 12 Months | ||||
| Work Progress Details | |||
|---|---|---|---|
| Physical progress | 87 % | ||
| Current status | All work completed including BC. Hand rail, approach crash barrier, drain connection and painting works in progress. Railway portion - All works completed | ||