Koduvally ROB

Back View Gallery View Progress

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 20
Technical Sanction Order Number Dated Amount(crores)
RBDCK/T 301/TS-19/2021-22 18.10.2021 19
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.132/2017/PWD 04.02.2017 37.38
District Kannur
LAC Thalassery
Location
Project Details
Actual Start Date 04.01.2021
Contractor(s) M/s SPL Infrastructure Pvt. Ltd
Project Management Consultant RITES
Category Road Over Bridges
LC No 230
Railway (km) 738/3-4
Length Including Approaches 313.60
Width of ROB 10.05
GAD Status APPROVED
No of Lanes 2
Financial Details
AS Amount(crores) 20
Revised AS Amount(crores) 37.38
Funded By KIIFB
Project Outlay(crores) 26.42
TS Amount(crores) 19
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/ROB/T301/ROB/14 25.06.2020 222.7
Agreement Details
Agreement No Agreement Date Agreed Amount(crores) Site Handover Date Period of Completion Actual Date of Completion
RBDCK/ROB/T44/28/2021 04.01.2021 251.48 12 Months
Work Progress Details
Physical progress 55 %
Current status All Foundation and substructure works are completed up to the pier. Girder erection and deck slab completed except adjacent & P8-A2 span. 95% of Drain work completed. 6/10 deck slab concrete completed, reinforcement work of one in progress. Girder erection & deck slab concrete for adjacent and P8-A2 span can be completed only after the completion of the railway portion. Railway portion - Pile, Pile cap, Pier & pier cap are completed.