General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.1324/2016/PWD | 27.09.2016 | 20 | |
Technical Sanction | Order Number | Dated | Amount(crores) |
RBDCK/T 30 I /TS-09 / 2021-22 | 09.08.2021 | 15.6 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.665/2017/PWD | 19.05.2017 | 22.61 | |
District | Thrissur | ||
LAC | Chalakudy | ||
Location |
Project Details | |
---|---|
Actual Start Date | 04.01.2021 |
Contractor(s) | M/s SPL Infrastructure Pvt. Ltd |
Project Management Consultant | RITES |
Category | Road Over Bridges |
LC No | 56 |
Railway (km) | 70/300-400 |
Length Including Approaches | 297.57 |
Width of ROB | 10.15 |
GAD Status | APPROVED |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 20 |
Revised AS Amount(crores) | 22.61 |
Funded By | KIIFB |
Project Outlay(crores) | 19.96 |
TS Amount(crores) | 15.6 |
Tender Details | |||
---|---|---|---|
Tender No | Dated | Tender Amount(crores) | RBDCK/ROB/T301/ROB/14 | 25.06.2020 | 222.7 |
Agreement Details | |||||||
---|---|---|---|---|---|---|---|
Agreement No | Agreement Date | Agreed Amount(crores) | Site Handover Date | Period of Completion | Actual Date of Completion | ||
RBDCK/ROB/T44/28/2021 | 04.01.2021 | 251.48 | 12 Months |
Work Progress Details | |||
---|---|---|---|
Physical progress | 94 % | ||
Current status | All structural works has been completed. Street light and other finishing works are progressing. Railway Portion - Railway Deck slab works completed. Parapet wall works are in progress. |