Chirangara ROB

Back View Gallery View Progress

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 20
Technical Sanction Order Number Dated Amount(crores)
RBDCK/T 30 I /TS-09 / 2021-22 09.08.2021 15.6
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.665/2017/PWD 19.05.2017 22.61
District Thrissur
LAC Chalakudy
Location
Project Details
Actual Start Date 04.01.2021
Contractor(s) M/s SPL Infrastructure Pvt. Ltd
Project Management Consultant RITES
Category Road Over Bridges
LC No 56
Railway (km) 70/300-400
Length Including Approaches 297.57
Width of ROB 10.15
GAD Status APPROVED
No of Lanes 2
Financial Details
AS Amount(crores) 20
Revised AS Amount(crores) 22.61
Funded By KIIFB
Project Outlay(crores) 19.96
TS Amount(crores) 15.6
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/ROB/T301/ROB/14 25.06.2020 222.7
Agreement Details
Agreement No Agreement Date Agreed Amount(crores) Site Handover Date Period of Completion Actual Date of Completion
RBDCK/ROB/T44/28/2021 04.01.2021 251.48 12 Months
Work Progress Details
Physical progress 94 %
Current status All structural works has been completed. Street light and other finishing works are progressing. Railway Portion - Railway Deck slab works completed. Parapet wall works are in progress.