Tanur-Theyyala ROB

Back View Gallery View Progress

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 20
Technical Sanction Order Number Dated Amount(crores)
RBDCK/T 301/TS-18/2021-22 18.10.2021 23.87
Revised Administrative Sanction Order Number Dated Amount(crores)
G.O. (Rt)No.700/2017/PWD 24.05.2017 34.16
District Malappuram
LAC Tanur
Location
Project Details
Actual Start Date 04.01.2021
Contractor(s) M/s SPL Infrastructure Pvt. Ltd
Project Management Consultant RITES
Category Road Over Bridges
LC No 172-A
Railway (km) 632/000-100
Length Including Approaches 406.69m
Width of ROB 10.15m
GAD Status APPROVED
No of Lanes 2
Financial Details
AS Amount(crores) 20
Revised AS Amount(crores) 34.16
Funded By KIIFB
Project Outlay(crores) 31.31
TS Amount(crores) 23.87
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/ROB/T301/ROB/14 25.06.2020 222.7
Agreement Details
Agreement No Agreement Date Agreed Amount(crores) Site Handover Date Period of Completion Actual Date of Completion
RBDCK/ROB/T44/28/2021 04.01.2021 251.48 12 Months
Work Progress Details
Physical progress 55 %
Current status All Foundation and substructure completed up to Pier cap (except railway portion). Girder erection completed except adjacent span. Drainage, Retaining wall, Service road & Deck slab works are progressing. Deck slab 5/10 completed. Railway portion - Pile, Pile cap, Pier & pier cap works are completed. Super structure works to be executed by Railways.