General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.1324/2016/PWD | 27.09.2016 | 10 | |
Technical Sanction | Order Number | Dated | Amount(crores) |
RBDCK/T 301/TS-13/2021-22 | 18.10.2021 | 26.16 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.884/2017/PWD | 25.06.2017 | 26.21 | |
District | Thiruvananthapuram | ||
LAC | Chirayinkeezhu | ||
Location |
Project Details | |
---|---|
Actual Start Date | 04.01.2021 |
Contractor(s) | M/s SPL Infrastructure Pvt. Ltd |
Project Management Consultant | RITES |
Category | Road Over Bridges |
LC No | 566 |
Railway (km) | 191/400-500 |
Length Including Approaches | 394.00 |
Width of ROB | 10.70 |
GAD Status | APPROVED |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 10 |
Revised AS Amount(crores) | 26.21 |
Funded By | KIIFB |
Project Outlay(crores) | 25.08 |
TS Amount(crores) | 26.16 |
Tender Details | |||
---|---|---|---|
Tender No | Dated | Tender Amount(crores) | RBDCK/ROB/T301/ROB/14 | 25.06.2020 | 222.7 |
Agreement Details | |||||||
---|---|---|---|---|---|---|---|
Agreement No | Agreement Date | Agreed Amount(crores) | Site Handover Date | Period of Completion | Actual Date of Completion | ||
RBDCK/ROB/T44/28/2021 | 04.01.2021 | 251.48 | 25.01.2018 | 12 Months |
Work Progress Details | |||
---|---|---|---|
Physical progress | 62 % | ||
Current status | All foundation and substructure works completed upto pier cap. Abutment wall and girder erection except adjacent span completed. Retaining wall work completed and embankment filling under progress. Drain work at A1 side RHS 25% and LHS 40% completed. At A2 side RHS 96% completed and remaining works are under progress. 6/11 deck slab concreting completed. Remaining deck slab sheet laying, reinforcement and concrete works under progress. Railway Portion - (Foundation , substructure and superstructure will be directly done by Railways) - Pile, pile cap, pier and pier cap completed. 3 out of 3 Girder erection completed. Deck slab concreting works completed. |