Mulamthuruthy ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1060/2013/PWD 31.07.2013
Technical Sanction Order Number Dated Amount(crores)
RBDCK/T 105/TS-24/2021-22 30.03.2022 20.77
Revised Administrative Sanction Order Number Dated Amount(crores)
G.O. (Rt) No. 227/2022/PWD 02.03.2022 21.28
District Ernakulam
LAC Piravom
Location
Project Details
Contractor(s) M/s Cherian Varkey Construction Co. (P) Ltd
Project Management Consultant RITES
Category Road Over Bridges
LC No 12
Railway (km) 16/200-300
Length Including Approaches 464.16
Width of ROB 7.50
GAD Status RAILWAY PORTION COMPLETED
No of Lanes 2
Financial Details
Revised AS Amount(crores) 21.28
Funded By Govt Funded
Project Outlay(crores) 21.28
TS Amount(crores) 20.77
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/ROB/T105/162/2022 05.04.2022 17.28
Agreement Details
Agreement No Agreement Date Agreed Amount(crores) Site Handover Date Period of Completion Actual Date of Completion
RBDCK/T 105/ROB/73/2023 01.02.2023 20.59 28.12.2022 18 months
Work Progress Details
Physical progress 41 %
Current status All Piles, Pile caps, Pier, Pier caps completed. 139/187 Precast Girders completed. Girder erection for 11/17 span completed. Slab works at P3 & P4 in progress. Retaining wall A1 side completed.