Current status |
LA requisition submitted to Dt. Collector Ernakulam on 23.08.2017. GAD approved on 29.01.2021. Stone planting completed and letter send to District Collector for joint site inspection. District Collector informed that the LA procedure expired (denova) due to the time limit exceed as per LA Act and want to submit fresh requisition. Revised requisition with alignment plan prepared and submitted to DC Ernakulam on 13.04.2021. Joint site inspection conducted on 17.06.2021. 4(1) notification published on 23.09.2021. SIA public hearing conducted on 16.10.2021. Expert committee meeting conducted on 02.02.2022 and report submitted to District Collector. 11(1) notification published on 23.03.2022. Land subdivision survey field work completed. RR Package hearing conducted on 29.11.2022. RR package approved.
Work order for structural valuation was issued on 28.11.2022. Structural valuation completed. RR package approved. 19 (1) published. BVR approved. Award enquiry completed. |