Current status |
Revised DPR approved by KIIFB on 12.02.2020 for an amount of Rs. 275.52 Cr.
LA requisition submitted to District Collector, Ernakulam on 27.10.2018. Stone planting completed and joint site inspection conducted on 28.01.2021. Contingency fund Rs. 50 lakhs sanctioned by KIIFB and released to LOA on 20.04.2021. SIA public conducted on 24.09.2021. 4(1) notification published on 03.08.2021. SIA final report submitted to District Collector on 23.10.2021. Expert Committee meeting conducted on 04.01.2022., report submitted to Govt. on 24.01.2022. Appropriate Govt. Order under section (8) issued on 25.01.2022. 11(1) notification published on 22.08.2022. Sub division survey works are progressing from LA Office. Structural Valuation is progressing. |