Perumbavoor Bypass- Phase I

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 20
Technical Sanction Order Number Dated Amount(crores)
RBDCK/T 172/TS-02/2023-24 03.08.2023 27.26
District Ernakulam
LAC Perumbavoor
Project Details
Contractor(s) Rajesh Mathew and Company
Project Management Consultant RITES
Category Road Projects
Length 1.037 km
Right of way 25m
No of Lanes 4
Financial Details
AS Amount(crores) 20
Funded By KIIFB
Project Outlay(crores) 79.8
TS Amount(crores) 27.26
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/RW/T172/266/2023 25.08.2023 22.76
Agreement Details
Agreement No Agreement Date Agreed Amount(crores) Site Handover Date Period of Completion Actual Date of Completion
RBDCK/T172/85/2024 16.03.2024 25.03 06.06.2024 18 months 06.12.2025
Work Progress Details
Current status DPR approved on 16.12.2017 for an amount of Rs.133.24 Cr. LA requisition submitted to Dt. Collector Ernakulam on 22.02.2018. Based on Hon'ble High court order for WP(C) 2451/2019, Government issued a GO (Rt) No. 1343/2019/PWD dtd 18.11.2019 to construct flyover over the PP road junction. Hence it was decided to execute the work in 2 phases to avoid the delay of work and KIIFB has approved to execute the projects in two phases. Revised DPR submitted to KIIFB for approval on 13.10.2020. KIIFB approved the DPR on 26.03.2022 for Rs.301.71 Crores. Phase I (CH 2.730km to CH 3.760km) : Land taken possession completed on 19.08.2023. Tender invited on 25.08.2023 and the same was opened on 07.10.2023. Two bids received. But one bidder did not qualify the technical bid. As this is the first tender, single bid could not be accepted. Hence work re-tendered on 3/11/2023. Technical bid opened on 15.12.2023. Financila bid opened on 10.01.2024. Request for negotiated was send to lowest quoted contractor M/s Rajesh Mathew & Company on 10.01.2024. They have submitted the negotiated estimate on 23.01.2024. LOA issued on 01.02.2024. Agreement executed on 16/03/2024. NTP issued on 06/06/2024. Preliminary works are progressing at site.