General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
G.O. (Rt)No.1324/2016/PWD | 27.09.2016 | 10 | |
District | Palakkad | ||
LAC | Pattambi |
Project Details | |
---|---|
Actual Start Date | 17.05.2018 |
Project Management Consultant | KITCO Ltd |
Category | Road Over Bridges |
LC No | 167 |
Railway (km) | 593/800-900 |
Length Including Approaches | 530 m |
Width of ROB | 10.15 |
GAD Status | Approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 10 |
Funded By | KIIFB |
Project Outlay(crores) | 31.31 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 40 % | ||
Current status | LA requisition submitted on 17.05.2018. LAO appointed on 4.08.2018. Contingency charge of Rs. 6,26,750/- released to LAO on 05.04.2019. GAD approved by Railways on 31.01.2023. Boundary stone planting completed on 26.04.2023. Joint inspection conducted on 26.05.2023. Contingency charge released to LAO. Public hearing completed. Expert committee meeting completed and report submitted to District Collector. |