Current status |
DPR approved by KIIFB on 22.05.2018 for an amount of Rs.12.62 Cr. LA requisition submitted on 12.07.2018. AS for LA received on 19.06.2019. 6(1) Notification published on 07.10.2019.
Due to protest from land owners stone planting obstructed, hence the project was put on hold. MLA requested to change the alignment in a manner which is acceptable to the land owners. Meeting was conducted by KIIFB in the presence Hon. MLA on 12.07.2022. KIIFB requested to revise the proposal and to submit the revised DPR on 22.09.2022. Revised DPR submitted to KIIFB on 08.02.2023.
Revised DPR approved by KIIFB on 22.05.2023. Revised LA requisition submitted to DC on 29.05.2023. Boundary stone planting was completed on 19.06.2023. Joint inspection with LAO was conducted on 02.08.2023. Contingency charge released to LAO on 07/11/2023. 4(1) Notification published on 16/12/2023.. SIA public hearing completed on 07/02/2024. SIA report was approved by DC and expert committee report submitted to DC. 11(1) notification published on 05.03.2024. BVR preparation in progress. |