Current status |
DPR approved on 22.5.2018 for an amount of Rs.30.56 Cr. GAD approved by Railways on 02.03.2023.
Requisition for acquiring additional land as per Railway's direction was submitted to DC, Kottayam on 23.04.2022. Stone planting completed on 07.05.2022. Joint site inspection with Special Tahsildar conducted on 08.06.2022. 19(1) declaration published on 14.07.2022. DVS approved by DC.
Award passed for 61 cases out of 68. WP(C) 18680/2021 disposed on 06.01.2025. Now W.A. No. 227/2025 has been filed. Additional fund request of Rs. 8,70,415 /- has been submitted by LAO. Fund transfer for land owners in progress. |