Projects

Kuttiyadi Bypass

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 10
Technical Sanction Order Number Dated Amount(crores)
RBDCK/ T 206/ TS - 06/ 2023-24 14.12.2023
District Kozhikode
LAC Kuttiady
Project Details
LA status
Project Management Consultant KITCO Ltd
Category Road Projects
Length 1.462 km
Right of way 12 m
No of Lanes 2
Financial Details
AS Amount(crores) 10
Funded By KIIFB
Project Outlay(crores) 37.96
Work Progress Details
Current status KIIFB approved on 09.11.2018 for an amount of Rs. 37.96 Cr Cr. Revised requisition submitted to DC, Kozhikode on 12.01.2021. As per the decision of District Collector revised alignment plan submitted to District Collector. Revenue AS obtained as per G.O.(Rt) No. 536/2012/RD dated 09.02.2021. Survey works for planting boundary stone again started and interrupted by public. WPC-5585/2021 filed by Shri. Krishnan Nair before Hon'ble HC for changing alignment on 01.03.2021. A joint meeting was conducted on 08.03.2022, by MLA Kuttiyadi in the presence of panchayath representatives and stake holders and it was decided to start the boundary stone laying at the earliest. Boundary stone laying was completed on 20.03.2022. Joint inspection conducted. 4(1) notification published on 30.05.2022. As requested by LAO, additional stones were planted and joint inspection conducted on 01.07.2022. SIA public hearing conducted on 25.08.2022. Expert committee report submitted to DC. 11(1) notification published on 12.01.2023. Survey work completed & Sub division survey works are progressing. BVR approved. Meanwhile, MLA and Local body representatives informed the willingness of the land owners for the advance possession and directed to proceed with Tendering procedures to avoid the delay. Hence requested to convene TS committee for issuing TS on 25.08.2023. TS committee convened on 14/12/2023 & technical sanction has been issued on 16/12/2023. Work tendered on 27.01.2024. Technical bid opened on 28/02/2024 and Financial bid opened on 12/03/2024. Lowest bidder was M/s BAAB Constructions. But, M/s The Uralungal Labour Contract Co-Operative Society has informed that they are eligible for price preference up to 10% by referring government orders G.O (Ms) No.21/ 2022/ PWD dated 29.07.2022, G.O (Ms) No.41/ 2020/ PWD dated 19.03.2020 and G.O (Ms) No.135/ 97/ Co – op dated 13.11.1997. RBDCK is not able to take final decision in light of the above Government Orders and subsequent legal opinion. Hence, letter no. RBDCK/ T 206/ Vol III/ 1584 dated 29.06.2024 we had requested GoK for a suitable advice at the Government Level regarding the finalisation of Tender. Parallelly LA work were proceeding on the other side. Vide letter B1/283/2019 dated 27/06/2024 fund request from LAO has received. Since we have a shortage of fund in the sub project approved by KIIFB, we have requested for the sub project revision for an amount of Rs. 39,45,73,159/- on 05/07/2024 in the KIIFB portal. Subproject for amount 39.42 Cr was approved. Hence package deviation has initiated for LA for an amount of Rs. 13.09Cr. LA cost received from KIIFB and the same has been remitted to LAO Koyilandy. Although all land owners initially provided consent for construction and its related works on the land to be acquired, later raised objection. Hence, NTP is not issued to the contractors.