Current status |
DPR was approved by KIIFB on 18.03.2019 for an amount of Rs.30.93 Cr. LA requisition submitted on 04.10.2019. AS for LA GO(Rt) No 3108/2019/RD dt.30.10.2019. GAD approved by Railways on 22.09.2023.
Request letter for NOC submitted to Regional Officer, NHAI, TVM on 04.05.2022. Reminder request submitted to Regional Officer, NHAI, TVM on 13.07.2022, 04.07.2023, 23.11.2023 & 15.04.2024. Meeting convened on 16.05.2024. Resurvey for incorporating NHAI row in alignment was conducted on 06.06.2024. Revised Alignment submitted to NHAI on 06.07.2024. Meeting convened on 12.07.2024. Additional drawings wanted by NHAI submitted to NHAI on 25.10.2024 |