Atlantis ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 50
District Ernakulam
LAC Ernakulam
Location
Project Details
Actual Start Date 15.02.2019
Project Management Consultant KITCO Ltd
Category Road Over Bridges
LC No 75A
Railway (km) 108/6-7
Length Including Approaches 523.92
Width of ROB 20.00
GAD Status Approved
No of Lanes 4
Financial Details
AS Amount(crores) 50
Funded By Government
Project Outlay(crores) 89.774
Work Progress Details
Physical progress 25 %
Current status GAD approved by Railways on 30.01.2023. Land taken possession in progress. 33/39 holdings handed over to RBDCK balance is pending due to WP(c) in Hon. high Court. TS will be convened after getting entire land from LAO. Demolition of structures in the acquired land in progress. Estimate Revision in progress.