Nedupuzha ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO (Rt)No.942/2017/PWD 10.07.2017 30
District Thrissur
LAC Ollur
Project Details
Actual Start Date 23.01.2019
Project Management Consultant KITCO Ltd
Category Road Over Bridges
LC No 24
Railway (km) 35/7-8
Length Including Approaches 750 m
Width of ROB 10.20 m
GAD Status APPROVED
No of Lanes 2
Financial Details
AS Amount(crores) 30
Funded By KIIFB
Project Outlay(crores) 31.042
Work Progress Details
Physical progress 50 %
Current status DPR approved by KIIFB on 26.10.2018 for an amount of Rs.31.042 Cr. Revised requisition including new survey numbers submitted to DC and LAO on 18.08.2020. 4(1) notification published on 26.08.2020. 11(1) Notification published on 26.10.2021. 19(1) published on 04.04.2023. GAD was already approved. But now the Project comes under 3rd line alignment. Vide letter dated 11.07.2022, Railway informed that GAD of ROB’s between Ernakulam and Shornur will be approved only after finalization of 3rd line. Award enquiry put on hold by Hon. Revenue Minister as the works falls in 3rd line alignment. During the meeting held on 26/10/2023 in the presence of Hon'ble Revenue Minister, Railway informed that they will issue NOC for continuing Land Acquisition. On 3/11/2023, Railway issued NOC and hence RBDCK requested District Collector to continue the Land Acquisition vide our letter dated 07/11/2023. LA nearing completion. As directed by Railways modified GAD submitted to Railways on 16.11.2023. Final GAD after incorporating the comments from Railways submitted on 09.01.2024. Awaiting approval of GAD from Railways.