Current status |
DPR approved by KIIFB on 16.03.2019 for an amount of Rs.28.23 Cr. LA requisition submitted on 11.06.2019. LA can be taken up only after the approval of GAD.
Project was pending due to Semi High Speed Rail project of KRDCL. On 06.12.2022, KRDCL had informed to go ahead with the construction of ROBs without considering the silver line alignment and RBDCK intimated the same to Railways on 08.12.2022. Railways directed to submit revised GAD for all ROBs long pending due to Silver line vide letter dated 14.03.2023.
Appointed the Consultancy M/s JH for the revision of GAD and alignment on 17.03.2023. Revised GAD submitted to Railways on 04.07.2023. LUS inspection conducted on 22.06.2023.LUS report submitted & requested railways for the approval of submitted GAD on 09.08.2023. Reminder letter submitted on 27.10.2023. Railways have proposed to resubmit this GAD with some changes on 10.11.2023. Revised GAD submitted on 27.02.2024. Reminder letter sent on 22.04.2024, 04.06.2024 and 22.08.2024.
GAD revised again by adding SV load details & submitted by 04.11.2024 |