Current status |
DPR approved by KIIFB on 28.06.2019 for an amount of Rs.34.9 Cr. LA to be taken up after getting approval of GAD from railways.
Railways requested for P&E charges and the amount was released to Railways on 30.05.2022. Revised GAD submitted to Railways on 13.06.2022. Reminder letter sent on 30.06.2022. Vide letter dated 11.07.2022, Railway informed that GAD of ROB’s between Ernakulam and Shornur will be approved only after finalization of 3rd line.
Joint Site inspection held on 10/10/2023 along with Railways. Awaiting NOC from Railways. |