Current status |
DPR approved by KIIFB on 26.06.2019. GAD approved by Railways on 16.03.2023. LA requisition submitted to District Collector on 07.08.2019.
6(1) notification published on 26.07.2022. Boundary stone planting completed and joint site inspection conducted on 17.09.2022. Contingency charge of Rs. 48 lakhs released to LAO. 4(1) notification published on 21.11.2022. 11(1) notification published on 03.08.2023. Survey works in progress. Valuation of structures completed and submitted to LAO. Fund request submitted by LAO and fund transfer in progress. |