Current status |
DPR approved by KIIFB on 28.06.2019 for an amount of Rs.37.28 Cr. LA Requisition submitted to DC on 07.08.2019. On 11.07.2022, Railway had given in-principle approval for starting the land acquisition. GAD approved by Railways on 16.03.2023.
6(1) notification published on 26.07.2022. Boundary stone planting completed and joint site inspection conducted on 17.09.2022. Contingency charge of Rs. 48 lakhs released to LAO. 4(1) notification published on 21.11.2022. 11(1) notification published on 03.08.2023. Survey works in progress. Valuation of structures is in final stage. |