Current status |
LA Requisition submitted to DC on 07.08.2019. On 11.07.2022, Railway had given in-principle approval for starting the land acquisition. GAD approved by Railways on 16.03.2023.
6(1) notification published on 26.07.2022. Boundary stone planting completed and joint site inspection conducted on 17.09.2022. Contigency charge of Rs. 48 lakhs released to LAO. SIA agency appointed. 4(1) notification published on 21.11.2022. SIA public hearing completed on 13.01.2023. Expert committee report submitted to DC on 14.02.2023. 11(1) notification published on 03.08.2023. Survey works in progress. Structural Valuation is in progress. |