Current status |
DPR approved by KIIFB on 28.06.2019 for an amount of Rs.19.33 Cr. LA requisition submitted to District Collector on 18.11.2019. LAO appointed as the Special Tahsildar LA KIIFB Kottayam. GAD approved by Railways on 14.11.2022.
As the resurvey works had been completed at that location after the submission of requisition, LAO directed to submit the revised LA plan. Revised LA requisition submitted to District Collector on 07.10.2022. 6(1) notification published on 27.10.2022. Boundary stone planting completed and joint inspection with Revenue department is conducted on 12.01.2023. Contingency charges released to LAO. 4(1) notification published on 26.06.2023. SIA public hearing conducted on 14.08.2023. Expert committee formed and report approved by District Collector on 22/03/2024. 11(1) notification published on 20.06.2024. Survey works in progress. Structural valuation in progress. |