General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.46/2020/PWD | 13.01.2021 | 51.73 | |
District | Kollam | ||
LAC | Kunnathur | ||
Location |
Project Details | |
---|---|
Category | Road Over Bridges |
LC No | 61 |
Railway (km) | 132/900 - 133/000 |
Length Including Approaches | 533 m |
Width of ROB | 10.20 m |
GAD Status | Approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 22.51 |
Revised AS Amount(crores) | 51.73 |
Funded By | KIIFB |
Project Outlay(crores) | 49.94 |
Work Progress Details | |||
---|---|---|---|
Current status | DPR approved by KIIFB on 26.02.2021 for an amount of Rs.49.94 Cr. GAD approved by Railways on 12.07.2022. LA requisition submitted to District Collector Kollam on 22.08.2022. 11(1) Notification published on 01/11/2023. Fund request received from LAO and is under process. |