General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.46/2020/PWD | 13.01.2021 | 51.73 | |
District | Kollam | ||
LAC | Kunnathur | ||
Location |
Project Details | |
---|---|
Category | Road Over Bridges |
LC No | 61 |
Railway (km) | 132/900 - 133/000 |
Length Including Approaches | 533 m |
Width of ROB | 10.20 m |
GAD Status | Approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 22.51 |
Revised AS Amount(crores) | 51.73 |
Funded By | KIIFB |
Project Outlay(crores) | 49.94 |
Work Progress Details | |||
---|---|---|---|
Current status | DPR approved by KIIFB on 26.02.2021 for an amount of Rs.49.94 Cr. GAD approved by Railways on 12.07.2022. LA requisition submitted to District Collector Kollam on 22.08.2022. Sp. Tahsildar LA1 Kollam is appointed as LAO. 6(1) notification published on 29.09.2022. Contingency charge of Rs. 3,052,179.00 released to LAO on 18.11.2022. Boundary Stone Planting Completed on 10.01.2023. 4(1) notification published on 04.01.2023. 11(1) Notification published on 01/11/2023. BVR approved. Structural valuation is progressing. Awaiting fund request from LAO. |