09.08.2021 - 14.08.2021
View previous reports View Project
Weekly Progress From 09.08.2021 - 14.08.2021
Sl No Item Description Executed Quantity Remarks
1 Initial Pile load test completed
2 Utility Shifting Work in Progress, Electricity board followup for shifting/ removal of EB lines/Posts.
3 Piling works - A1 Side : Making approach path for piling activities