21.12.2020 - 27.12.2020
View previous reports View Project
Weekly Progress From 21.12.2020 - 27.12.2020
Sl No Item Description Executed Quantity Remarks
ACADEMIC BUILDING
1 Columns & Retaining wall (A &B)- Centering and shuttering 57.6 m2
2 Columns, Beam, Slab - Steel Reinforcement 2955 kg
3 Concrete - Retaining wall & Columns Zone B & Zone A 15.10 m3
INTERNATIONAL GUEST HOUSE
4 Beam and Slab - Centering and shuttering 142 m2
5 Beam, Slab - Steel Reinforcement 735 kg
ENGINEERING BLOCK
6 Columns - Steel Reinforcement 651 kg
7 Column - Centering and shuttering 21.2 m2
8 Columns Concrete 1st floor 1.2 m3
CAMPUS REJUVENATION
9 Earthwork Excavation 17 m3
10 Reinforcement 350 kg
11 Centering and shuttering (sq.m) 52 m2
12 Drain RCC 7.1 m3