28.12.2020 - 02.01.2021
View previous reports View Project
Weekly Progress From 28.12.2020 - 02.01.2021
Sl No Item Description Executed Quantity Remarks
ACADEMIC BUILDING
1 Centering and shuttering (sqm) Column @ Zone A & B , Lintel, Beam Grid G’ and Slab @+5.10 lvlZone B 312.50 Sq.m
2 Steel Reinforcement (kg) Zone A & B Columns in GF 850 Kg
3 RCC –M30(cum) Columns Zone B & Zone A, Zone B Beam and Slab @ +5.10 lvl 109.96 Cu.m
INTERNATIONAL GUEST HOUSE
4 Steel Reinforcement (kg) Beam and Slab @ +3.30 lvl 3300 Kg
ENGINEERING DEPARTMENT BLOCK
5 Centering and shuttering (sqm) Columns in First Floor & lift Columns 8.50 Sq.m
6 RCC –M30(cum) Columns in First Floor 2.685 Cu.m
7 Steel Reinforcement (kg) Staircase 40 Kg
CAMPUS REJUVENATION
8 Centering and Shuttering (sqm) 50 Sq.m
9 Steel Reinforcement (kg) 1200 Kg
10 Drain RCC (cum) 8.40 Cu.m
FACILITATION CENTRE
11 Random Rubble masonry(m3) Foundation and basement No works were carried out