04.01.2021 - 10.01.2021
View previous reports View Project
Weekly Progress From 04.01.2021 - 10.01.2021
Sl No Item Description Executed Quantity Remarks
1 ACADEMIC BUILDING : Centering and shuttering @Column @ Zone A & B, Beam and Slab @+5.10 lvl,Lintel Beam in Zone B 139.49 sqm
2 Steel Reinforcement @ Zone A & B Columns in GF, Beam and Slab @ +5.10 lvl 2585 kg
3 RCC – M30 @ Columns Zone B & Zone A, Zone B Lintel Beam. 10.54 cum
4 INTERNATIONAL GUEST HOUSE : Steel Reinforcement @ Beam and Slab @ +3.30 lvl 4550 kg
5 Centering and shuttering @ Beam and Slab @ +3.30 lvl 21 sqm
6 ENGINEERING DEPARTMENT BLOCK : Centering and shuttering @ Beam and Slab @ +6.30 lvl 122.72 sqm
7 RCC –M30 @ Columns in First Floor 5.18 cum
8 CAMPUS REJUVENATION : Centering and Shuttering 39.50 sqm
9 Steel Reinforcement 800 kg
10 Drain RCC 4.50 cum