Projects

11.01.2021 - 17.01.2021
View previous reports View Project
Weekly Progress From 11.01.2021 - 17.01.2021
Sl No Item Description Executed Quantity Remarks
ACADEMIC BUILDING
1 Centering and shuttering @Column @ Zone A & B , , Beam and Slab @+5.10 lvl 65 sqm
2 Steel Reinforcement @ Zone A & B Columns in GF , Beam and Slab @ +5.10 lvl 2700 kg
3 RCC –M30 @ Columns Zone B & Zone A, Zone B Lintel Beam. -
INTERNATIONAL GUEST HOUSE
1 Steel Reinforcement @ Beam and Slab @ +3.30 lvl 2600 kg
2 Centering and shuttering @ Beam and Slab @ +3.30 lvl 40 sqm
ENGINEERING DEPARTMENT BLOCK
1 Centering and shuttering @ Beam and Slab @ +6.30 lvl 195 sqm
2 RCC –M30 @ Columns in First Floor -
CAMPUS REJUVENATION
1 Centering and Shuttering 128 sqm
2 Steel Reinforcement 1000 kg
3 Drain RCC 11 cum
FACILITATION CENTRE
1 Random Rubble masonry (cum) @ Foundation and basement Not Provided