18.01.2021 - 24.01.2021
View previous reports View Project
Weekly Progress From 18.01.2021 - 24.01.2021
Sl No Item Description Executed Quantity Remarks
ACADEMIC BUILDING
1 Centering and shuttering @ Column @ Zone A & B , Beam and Slab @+5.10 lvl 52 sqm
2 Steel Reinforcement @ Zone A & B Columns in GF , Beam and Slab @ +5.10 lvl 1150 kg
3 RCC –M30 @ Columns Zone B & Zone A, Zone B Lintel Beam.
INTERNATIONAL GUEST HOUSE
4 RCC M30 @ Beam and Slab @ +3.30 lvl 95.50 cum
5 Steel Reinforcement @ Stair 1&2 335 kg
6 Centering and shuttering @ Stair 1&2 26 sqm
ENGINEERING DEPARTMENT BLOCK
7 Centering and shuttering @ Beam and Slab @ +6.30 lvl 140 sqm
8 Steel Reinforcement @ Beam and Slab @ +6.30 lvl 2800 kg
CAMPUS REJUVENATION
9 Centering and Shuttering @ Location 3-4 and1-2 90.50 sqm
10 Steel Reinforcement @ Location 3-4 and1-2 2550 kg
11 Drain RCC @ Location 3-4 and1-2 22 cum