25.01.2021 - 31.01.2021
View previous reports View Project
Weekly Progress From 25.01.2021 - 31.01.2021
Sl No Item Description Executed Quantity Remarks
ACADEMIC BUILDING
1 Centering and shuttering 75 sqm Beam and Slab @ +5.10 lvl ,Sunshade, Stair case
2 Steel Reinforcement 2250 kg Zone B Beam and Slab @ +5.10 lvl
INTERNATIONAL GUEST HOUSE
1 Centering and shuttering 190 sqm Beam and Slab @ +3.30 lvl
2 Steel Reinforcement 6000 kg Beam and Slab @ +6.30 lvl
CAMPUS REJUVENATION
1 Centering and Shuttering 115 sqm Location 3-4 and1-2
2 Steel Reinforcement 850 kg
3 Drain RCC 9.50 cum Location 3-4 and1-2