01.02.2021 - 07.02.2021
View previous reports View Project
Weekly Progress From 01.02.2021 - 07.02.2021
Sl No Item Description Executed Quantity Remarks
ACADEMIC BUILDING
1 Centering and shuttering 39.00 sqm Beam and Slab @ +5.10 lvl ,Sunshade, Stair case
2 Steel Reinforcement 670 kg Zone B Beam and Slab @ +5.10 lvl
3 RCC –M30 127 cum Columns Zone B & Zone A, Zone B Lintel Beam
INTERNATIONAL GUEST HOUSE
1 Steel Reinforcement 800 kg Beam and Slab @ +3.30 lvl
ENGINEERING DEPARTMENT BLOCK
1 Steel Reinforcement 200 kg Beam and Slab @ +6.30 lvl
CAMPUS REJUVENATION
1 Centering and Shuttering 107 sqm Location 5-6 and 1-2
2 Steel Reinforcement 1300 kg Location 3-4 and 5-6
FACILITATION CENTRE
1 Random Rubble masonry(m3) - Foundation and basement - No works due to shortage of Manpower