Weekly Progress From 22.02.2021 - 28.02.2021 | ||||
---|---|---|---|---|
Sl No | Item Description | Executed Quantity | Remarks | |
ENGINEERING DEPARTMENT BLOCK | ||||
1 | RCC –M30(cum) | 106 cum | Beam and Slab @ +6.10 LVL | |
CAMPUS REJUVENATION | ||||
1 | Centering and Shuttering (sqm) | 120 sqm | Location 3-4 & Location 6 to existing drain | |
2 | Steel Reinforcement (kg) | 200 kg | Location 3-4 & Location 6 to existing drain | |
3 | Drain RCC (cum) | 11 cum | Location 3-4 & Location 6 to existing drain |