General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
District | Alappuzha | ||
LAC | Mavelikara |
Project Details | |
---|---|
LA status | |
Category | Road Over Bridges |
LC No | 28 |
Railway (km) | 106/300-400 |
Length Including Approaches | 494.52 m |
Width of ROB | 10.20 m |
GAD Status | Approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 22.51 |
Funded By | KIIFB |
Project Outlay(crores) | 38.22 |
Work Progress Details | |||
---|---|---|---|
Current status | DPR approved on 09.08.2020 for an amount of Rs. 38.22 Cr. GAD approved by Railways on 12.07.2022. Land taken possession completed on 05/03/2024. The work was retendered on 11.02.2025. Technical bid opened on 15.03.2025 and 4 Bids received. The lowest bidder has quoted 18% above estimate but submitted finacial bid was unbalanced, hence rejected. Work was retendered on 18.06.2025. |