| Current status |
DPR approved on 09.08.2020 for an amount of Rs. 38.22 Cr. GAD approved by Railways on 12.07.2022.
Land taken possession completed on 05/03/2024. The work was retendered on 11/02/2025. Technical bid opened on 15/03/2025. 4 bids received. The lowest bidder has quoted 18% above estimate but submitted financial bid was unbalanced, hence rejected. Work was retendered on 18.06.2025. Technical Bid opened on 19/07/2025 and 3 bids received. Financial bid opened on 12.09.2025. The work was awarded to L1 bidder M/s M Rajkumar and LOA issued on 04.11.2025. |