Current status |
DPR approved on 09.08.2020 for an amount of Rs. 38.22 Cr. GAD approved by Railways on 12.07.2022.
Land taken possession completed on 05/03/2024. TS issued on 09.07.2024. Request for revised Financial sanction submitted to KIIFB on 30/07/2024. Demolition of structures and tree cutting is completed. Vide order no PWD 011-15/APR-3/2024/KIIFB dated 23.11.2024, KIIFB has accorded sanction for revised FS of Rs. 48.33 Cr. Work tendered on 13.12.2024 and technical bid opened on 28.01.2025. Only one bidder has participated and hence work was retendered on 11/02/2025. Technical opened on 15/03/2025. Technical bid evaluation under progress. |