Sl. No. Project Name Current Status of Work Physical Progress
1 CUSAT Package 1 (Kalamassery Main Campus) Under Construction
18%
2 Eravipuram ROB Under Construction
55%
3 CUSAT Package 3 (Electrical) Under Construction
90%
4 Tanur-Theyyala ROB Under Construction
57%
5 Maliyekkal ROB Under Construction
85%
6 Koduvally ROB Under Construction
65%
7 Airport Seaport Road Phase II (HMT TO NAD) Under Construction
95%
8 Thirunavaya-Thavanur River Bridge Under Construction
0%
9 Mulamthuruthy ROB Under Construction
41%
10 Chirayinkeezhu ROB Under Construction
51%
11 Vadanamkurussi ROB Under Construction
58%
12 Akathethara ROB Under Construction
75%
13 Kanjirapalli Bypass Under Construction
10%
14 Chirangara ROB Under Construction
80%